广陵体操馆争分夺秒抢抓工期Guangling gymnasts scramble for time to seize the time limit
广陵体操馆争分夺秒抢抓工期
工人正紧锣密鼓安装屋面面板。
“天气转好,明天室外工人正常作业!”“体操馆和市民广场的连接桥基础桩年前必须结束,望相关单位从紧安排,二十四小时人停机不停!确保按预定工期完成!”……1月27日晚,广陵体操馆联络群陆续发出施工通知。
历时大半年建设的广陵体操馆项目,总投资6.5亿元,是承办省运会体操项目比赛的一个重点工程,采用了大跨度悬挑结构架空连梁,室内净高达20多米,跨度最长达到61米,建成后能够容纳3000多观众,不仅有标准的赛事场地,还有训练室、健身房、配套商业等向市民开放的休闲健身场所,项目预计3月底内部装修结束,5月份交付进行试运营。
1月29日下午,笔者走进体操馆项目建设现场,室外场地堆满了装修材料,上面积雪还未融尽,2组大吊机井然作业,外墙拆了一半的脚手架上还有不少工人在忙着幕墙装饰,冰天雪地里到处洋溢着热火朝天的干事豪情。“我们要保证春节前脚手架全部拆除,现场大理石、玻璃幕墙等装修材料全部安装完毕。”
目前,项目地面管网已经全部下放,道路开始做面基。跟着项目总包单位负责人孙乐羊走进内场,体操馆内部300多号装修人员紧锣密鼓地施工中,“目前内部装修基层基本完成,准备封板,过完年就着手贴砖了。”
说起近日大雪,孙乐羊告诉笔者,现在项目已经进入发力阶段了,进度都卡得很紧,全体人员倾团出动,加班加点抢抓进度,遇到特殊天气更要咬牙坚持。“从一开始接收到暴雪警报,我们就开始提前部署工作,召集各分包单位召开安全生产大会,安排下雪天24小时轮流值班,防止发生安全事故,工程上也及时调整了工作部位,室内照旧作业,停雪后室外继续施工。”
下雪期间,项目总指挥部也组织监理、设计等单位和各专业技术人员,走进施工工地,指明服务范围、区位,明确责任。“我们清理出常走的交通线路、坡道,做好防滑畅通工作,尤其是钢结构屋面,及时清雪减荷防塌。”孙乐羊说,“为了不耽误工人进场施工,我每天早早就到工地,和值班人员一起将几条主要道路清理出来。”
采访过程中,笔者还注意到,几名工作人员现场讨论起了室外亮化问题。孙乐羊告诉笔者,这样的现场讨论会已是常态,“我们每天驻守现场就是要协调解决好各类影响施工进度的问题,一旦发现必须及时沟通拿方案,确保项目保质按序时推进。”
据了解,项目装饰单位的工人大年初三就将提前复工,其他人员初六全面复工。“我老家在安徽,因为要提前准备复工的相关事宜,今年就留在扬州过年了。”装饰单位负责人王勇说,“项目到了关键节点,一切都要争分夺秒干!”
Guangling gymnasts scramble for time to seize the time limit
The workers are mounting the roofs of the roofs.
"The weather is better, and the outdoor workers are working tomorrow." "The connecting bridge foundation of the gymnasium and the public square must be finished before the year, and the related units are arranged tight, and twenty-four hours are stopped." Make sure that the schedule is completed! In the evening of January 27th, the Guangling gymnasium liaison group sent out the construction notice successively.
For a long time the construction of Guangling gymnasium project, a total investment of 650 million yuan, is a key project for the Provincial Games gymnastics competition, with a large span cantilever structure of overhead beam, indoor net up to more than 20 meters, the longest span of up to 61 meters, can be built to accommodate more than 3000 spectators, not only had the standard there are competitions, training room, gym, and other commercial facilities open to the public leisure fitness sites, the project is expected by the end of March the end of the internal decoration, delivered in May for trial operation.
The afternoon of January 29th, I walked into the gym for the project construction site, outdoor venues filled with decoration materials, on the snow not melts, 2 groups of large crane in operation, the scaffold walls demolished half there are many workers in the busy curtain wall decoration, in a world of ice and snow everywhere filled with the pride of general be in full swing. "We should guarantee all the demolition of the scaffold before the Spring Festival, and all the decoration materials, such as marble and glass curtain wall, are all installed."
At present, the ground pipe network of the project has been completely put down, and the road begins to make face base. Follow the project general contractor responsible person sun LeYang into the internal more than 300 gym decoration and construction "wildly beating gongs and drums, the interior decoration base basically completed, ready to board, over the years on the tiles."
Speaking of the recent heavy snow, Sun Leyang told reporters, now the project has entered the stage of force, progress are tight, all the staff in group dispatched work overtime to seize the progress, meet special weather to adhere to the teeth. "From the beginning to receive a blizzard warning we started work, deployed in advance, convened by the subcontractor held safety meeting, arrange snow days 24 hours shifts, to prevent the occurrence of safety accidents, timely adjustment of the work on the project site, indoor or outdoor operation, stop the continued construction of the snow."
During the snow season, the project headquarters also organized supervision, design and other units and professional technicians to enter the construction site, indicating the scope and location of the services, and making clear responsibilities. "We clean out the usual traffic lines, ramps, do a good job of smooth and smooth work, especially the steel structure roof, in time to reduce the snow to reduce the collapse." Sun Leyang said, "in order not to delay the construction of the workers, I go to the construction site early every day, with the staff on duty to clean up a few main roads."
In the course of the interview, the author also noticed that several staff members discussed the problem of outdoor lighting. Sun Leyang told me that such a live seminar is normal. "Every day we are stationed at the scene is to coordinate and solve all kinds of problems that affect the progress of construction. Once we find out, we must timely communicate with each other and get the plan to ensure that the quality of the project is pushed forward according to the order".
It is understood that the project decoration unit workers third days ahead of time will return to work, the other staff fully resumed. "My old family in Anhui, because to prepare for the rework of the related matters in advance, this year in Yangzhou for the new year." Wang Yong, the head of the decoration unit, said, "the project has come to the key node, and everything is going to work for the second."